PACE Kenya project first quarter progress report for year 2 annual work programme.

Published
The second year workplan was approved in December, 2002. Despite the holiday seasonand national elections, project activities still continued during the quarter. Follow-upinvestigations of the suspected Laikipia rinderpest outbreak were finalised. The projecttechnical assistant was recruited by AU/IBAR and reported in January, 2003.Update: Due to delay in receiving year 2 funds in time, it has become necessary to revisethe project's activity time chart. See the attached Annex H for details.Further, it has been noticed that the Year 2 project financing document contains someerrors that need to be corrected. For this reason, together with the need to revise theactivity time chart, an addendum is under preparation.